Installation and commissioning of rotary drum granulator:
1. Installation: The machine should be installed in accordance with the process flow, indicating the elevation and horizontal position, and installed at a tilt angle of 2-2.5 degrees (which can be adjusted by the user as needed). Both the bracket and transmission frame of this machine have foot holes, which can be installed on concrete.
2. Debugging: After the installation of the granulator is completed, it is necessary to first check whether the various components of the granulator are tightened. Then conduct a no-load test to observe if the steering is correct. If not, make adjustments. The noise of gears should also be uniform and not fluctuate high or low.
Precautions for operating rotary drum granulator:
Before starting up, check if there are any debris inside the machine.
2. Check if all parts of the machine are functioning properly.
3. After starting the machine, check if the rotation direction is correct. If it rotates in the opposite direction, stop and adjust immediately. Confirm smooth rotation, no noise, and no friction noise before starting production.
4. It is strictly prohibited for iron blocks, stones, wood and other debris to enter the machine to prevent damage to the equipment.
5. The gearbox must be lubricated with gear oil before production use, and the gear oil should be replaced every four months.
6. Gears, ring gears, rollers, pulleys, etc. all need to be filled with yellow dry oil.
7. Before shutting down, the internal materials must be completely discharged to prevent them from sticking to the cylinder. Prepare for the next start-up and facilitate the production of the next team.